CASE STUDY: Events and Festivals

Afro Nation 2026: A Fourth Year Delivering Beach Access at Praia da Rocha

Afro Nation Signaroad beach access install Trackway

In a nutshell:

  • Equipment used: SignaRoad, Preco-Track & Stadia XHD
  • Vehicles: 22 full truckloads across Europe on carnets
  • Distance travelled: 1560 miles UK to Portimao
  • Installation time: 6 days
  • Pack-up time:Beach cleared and returned to civic authority by 12 July
  • Size of team: Approx. 30 people — install & removal crew
Afro Nation Signaroad beach access install Trackway

Project Overview

Clients & Event: The Malachite Group & Made of You – Afro Nation 2026
Location: Praia da Rocha Beach, Portimão, Portugal
Event Dates: 3rd – 5th July 2026
Attendance: 38,000 festival-goers over three days
Coverage Area: 13,000 sqm of temporary road infrastructure
Challenge: Creating heavy-duty beach access for construction vehicles and festival infrastructure


The Challenge

Praia da Rocha needed to support articulated lorries and heavy cranes on sand entirely unsuited to such loads, so that staging, catering, and event infrastructure could be built and operated safely across a five-week window. Delivering the volume of trackway required meant moving 22 full truckloads across Europe on customs carnets within a tight installation timeline, all while contending with summer heat and the practical constraints of a remote beach location.


Our Solution

The Box Group deployed a comprehensive temporary road system combining two specialised products:

  • Multi-product deployment: SignaRoad (1,600 panels / 8,512 m²) for primary access routes, combined with Preco-Track (660 panels / 3,960 m²) — trialed for the first time in low-traffic areas — plus a Stadia XHD stillage, totaling approx. 13,000 m² across the majority of Praia da Rocha.
  • Rapid mobilisation: The Box Group responded as soon as the event was confirmed, coordinating 22 full truckloads across Europe under carnet within a tight installation window.
  • Extended in-situ deployment: Trackway remained down for 5 weeks, enabling staging, catering, and wider event infrastructure to be built, operated, and dismantled around it.

Outcome

  • All operational objectives met — trackway performed as required throughout install, the five-week deployment, and de-rig.
  • Preco-Track successfully trialled for suitability in low-traffic areas, proving effective for future deployments.
  • 22 full truckloads delivered across Europe within a tight timeline, with no disruption to the wider event build.
  • Beach handed back to Portimão Municipal Council on schedule, on the morning of 12 July.

Long-term Partnership

The project’s outstanding success has secured Box Group’s role in the festival’s long-term partnership, cementing our position as the trusted temporary infrastructure partner for this world-class event.

Environmental Responsibility

Our temporary road system provided complete beach protection, ensuring the natural environment remained undamaged while supporting extensive festival construction activities.


Technical Innovation

This project showcased The Box Group’s ability to adapt standard installation techniques for unique event setups and environments. The panel configuration required:

  • Highly skilled operators familiar with alternative installation methods
  • Specialised training for local crew members
  • Real-time problem-solving for panel alignment challenges
  • Innovative approaches to working within regulatory constraints

Project Metrics

MetricAchievement
Total Coverage13,000 sqm
Installation Duration15 days across two phases
Vehicle Movements Supported1,500+ passes
Safety RecordZero incidents
Stakeholder Satisfaction100%
Environmental ImpactZero beach damage

Why The Box Group?

The continuing success over the last three years with the Afro Nation festival demonstrates Box Group’s unique capabilities:

  • Specialised expertise in challenging environments
  • Adaptable solutions tailored to unique site conditions
  • Regulatory compliance with local authority requirements
  • Reliable delivery under tight timeframes
  • Long-term partnership approach building lasting client relationships

For your next temporary road or ground protection project, discover how The Box Group’s innovative solutions can transform your site access challenges into operational success.

Ready to discuss your next event’s requirements? Contact our team today. Call  +44 (0) 020 8038 6131 or email hello@theboxgrp.com

 

We’re here to help

At The Box Group we know the integrity of your temporary operating environment is critical to success. Get it right, and the rest of the project can align and succeed.

Our solutions are much more than the provision of the right kit; they combine our years of experience with inventive thinking and a can do, positive mindset – to meet logistical challenges, enable operations, mitigate risk and complete missions. When there’s no room for error, our clients trust us to deliver.

testimonials and reviews icon

Download Your PDF

Download Brochure - With Title
Download Brochure - With Title